This open house was active from June 24-July 15, 2022. Information on this website may no longer be current. Email us for more information.

 

Schedules are subject to change.

 
  • Open house

    June 24-July 17, 2022
  • Stage 1

    July 2022-January 2023

    Median removal and sound wall installation.

  • Stage 2

    January-April 2023

    Temporary widening of Roy Rogers Road (south side)

  • Stages 3-4

    April 2023-February 2024

    WWSP pipeline installation (north side of Roy Rogers Road) and Roy Roger Road widening (north side).

  • Lavender Avenue closed at Roy Rogers Road

    2 weeks during Stage 3
  • Lynnly Way closed at Roy Rogers Road

    2 weeks during Stage 3
  • Stages 5-7

    February 2024-October 2024

    Final construction, construction of medians and islands and final paving and striping.