Lavender Avenue and Lynnly Way will each be closed at Roy Rogers Road for about two weeks during Stage 3 of construction.
Stage 1: Median removal and sound wall installation
Stage 2: Temporary widening of Roy Rogers Road (south side)
Stage 3: WWSP pipeline installation (north side of Roy Rogers Road)
Stage 4: Roy Rogers Road permanent widening (north side)
Stage 5: Roy Rogers Road permanent widening (south side)
Stage 6: Construction of medians and islands
Stage 7: Final paving and striping