Open house
June 24-July 17, 2022 -
Stage 1
July 2022-January 2023Median removal and sound wall installation.
-
Stage 2
January-April 2023Temporary widening of Roy Rogers Road (south side)
-
Stages 3-4
April 2023-February 2024WWSP pipeline installation (north side of Roy Rogers Road) and Roy Roger Road widening (north side).
-
Lavender Avenue closed at Roy Rogers Road
2 weeks during Stage 3 -
Lynnly Way closed at Roy Rogers Road
2 weeks during Stage 3 -
Stages 5-7
February 2024-October 2024Final construction, construction of medians and islands and final paving and striping.